Task Report: Write On

Task Start End Duration Completed Dependencies Total Cost Assigned Planned Start Start Variance Constraint Start Planned End End Variance Constraint End
0) Write On 9/1/17, 8:00 AM 5/18/18, 7:00 PM 3,831.25h 51.39%
1) PHASE 1: REQUIREMENTS AND CONCEPT DESIGN 9/1/17, 8:00 AM 10/31/17, 10:45 PM 899.75h 91.64%
1.1) Design Active Tip 9/1/17, 8:00 AM 10/3/17, 10:45 PM 486.75h 100% Andy
1.2) Reduce Stylus Size 9/1/17, 8:00 AM 10/3/17, 10:45 PM 486.75h 100% Curtis
1.3) App Development 9/1/17, 8:00 AM 10/3/17, 10:45 PM 486.75h 100% Mark
1.4) Design Charging Method 10/9/17, 8:00 AM 10/23/17, 4:00 PM 214.5h 0% Andy
1.5) System Designs 9/1/17, 8:00 AM 10/31/17, 10:45 PM 899.75h 100% Andy {33% of 100%}; Curtis {33% of 100%}; Mark {33% of 100%}
2) PHASE 2: DETAILED DESIGN, FABRICATION, ASSEMBLY 11/1/17, 8:00 AM 12/30/17, 10:45 PM 885h 76.49% 1.5
2.1) Test Stylus Tip 11/1/17, 8:00 AM 11/11/17, 10:45 PM 162.25h 100% Andy
2.2) Test Grip System 11/1/17, 8:00 AM 11/11/17, 10:45 PM 162.25h 100% Curtis
2.3) Test Tilt System 11/12/17, 8:00 AM 11/18/17, 10:45 PM 103.25h 100% Curtis
2.4) Test App 11/1/17, 8:00 AM 11/11/17, 10:45 PM 162.25h 80% Mark
2.5) Test Battery Life 11/13/17, 8:00 AM 11/18/17, 10:45 PM 88.5h 0% Mark
2.6) Test Charging System 11/13/17, 8:00 AM 11/18/17, 10:45 PM 88.5h 20% Mark
2.7) Design Fabrication 12/9/17, 8:00 AM 12/30/17, 10:45 PM 324.5h 80% Curtis {50% of 100%}; Mark {50% of 100%}
3) PHASE 3: TEST AND VERIFICATION 1/1/18, 8:00 AM 4/21/18, 9:00 AM 1,623.5h 13.75% 2
3.1) In-house Tests #1 1/1/18, 8:00 AM 1/6/18, 10:45 PM 88.5h 80% Andy
3.2) Field Test #1 1/7/18, 8:00 AM 1/13/18, 10:45 PM 103.25h 30% Mark
3.3) Design Verification / Validation #1 1/7/18, 8:00 AM 1/21/18, 10:45 PM 221.25h 70% Andy
3.4) Design adjustments #1 1/7/18, 8:00 AM 1/16/18, 10:45 PM 147.5h 30% Curtis; Andy; Mark
3.5) In-house Tests #2 2/7/18, 8:00 AM 2/13/18, 10:45 PM 103.25h 0% Andy
3.6) Field Test #2 2/14/18, 8:00 AM 2/20/18, 10:45 PM 103.25h 0% Mark
3.7) Design Verification / Validation #2 2/14/18, 8:00 AM 2/26/18, 10:45 PM 191.75h 0% Andy
3.8) Design adjustments Final 2/14/18, 8:00 AM 3/9/18, 10:45 PM 354h 0%
3.9) In-house Tests Final 3/10/18, 8:00 AM 3/17/18, 10:45 PM 118h 0% Andy
3.10) Tip drawings submitted 3/9/18, 4:00 PM 3/9/18, 4:00 PM 0%
3.11) Field Test Final 3/18/18, 8:00 AM 3/27/18, 10:45 PM 147.5h 0% Mark
3.12) Design Verification / Validation Final 3/11/18, 9:00 AM 4/4/18, 9:00 AM 354h 0% Andy
3.13) Design Manufacturing Plans 3/11/18, 9:00 AM 4/21/18, 9:00 AM 604.75h 0% Curtis
4) PROGRAM MANAGEMENT 9/8/17, 8:00 AM 4/24/18, 4:00 PM 3,371h 70.27%
4.1) WEEKLY AGENDAS 1/24/18, 3:00 PM 4/24/18, 4:00 PM 1,328.5h 21.43%
4.1.1) Create/Send 1/24/18, 3:00 PM 1/24/18, 4:00 PM 1h 100% Curtis
4.1.2) Create/Send 1/30/18, 3:00 PM 1/30/18, 4:00 PM 1h 100% Curtis
4.1.3) Create/Send 2/6/18, 3:00 PM 2/6/18, 4:00 PM 1h 100% Curtis
4.1.4) Create/Send 2/13/18, 3:00 PM 2/13/18, 4:00 PM 1h 0% Curtis
4.1.5) Create/Send 2/20/18, 3:00 PM 2/20/18, 4:00 PM 1h 0% Curtis
4.1.6) Create/Send 2/27/18, 3:00 PM 2/27/18, 4:00 PM 1h 0% Curtis
4.1.7) Create/Send 3/6/18, 3:00 PM 3/6/18, 4:00 PM 1h 0% Curtis
4.1.8) Create/Send 3/13/18, 3:00 PM 3/13/18, 4:00 PM 1h 0% Curtis
4.1.9) Create/Send 3/20/18, 3:00 PM 3/20/18, 4:00 PM 1h 0% Curtis
4.1.10) Create/Send 3/27/18, 3:00 PM 3/27/18, 4:00 PM 1h 0% Curtis
4.1.11) Create/Send 4/3/18, 3:00 PM 4/3/18, 4:00 PM 1h 0% Curtis
4.1.12) Create/Send 4/10/18, 3:00 PM 4/10/18, 4:00 PM 1h 0% Curtis
4.1.13) Create/Send 4/17/18, 3:00 PM 4/17/18, 4:00 PM 1h 0% Curtis
4.1.14) Create/Send 4/24/18, 3:00 PM 4/24/18, 4:00 PM 1h 0% Curtis
4.2) MEETING MINUTES 9/8/17, 8:00 AM 11/24/17, 9:00 AM 1,136.75h 100%
4.2.1) Minutes Compile 9/8/17, 8:00 AM 9/8/17, 9:00 AM 1h 100% Mark
4.2.2) Minutes Compile 9/15/17, 8:00 AM 9/15/17, 9:00 AM 1h 100% Mark
4.2.3) Minutes Compile 9/22/17, 8:00 AM 9/22/17, 9:00 AM 1h 100% Mark
4.2.4) Minutes Compile 9/29/17, 8:00 AM 9/29/17, 9:00 AM 1h 100% Mark
4.2.5) Minutes Compile 10/6/17, 8:00 AM 10/6/17, 9:00 AM 1h 100% Mark
4.2.6) Minutes Compile 10/13/17, 8:00 AM 10/13/17, 9:00 AM 1h 100% Mark
4.2.7) Minutes Compile 10/20/17, 8:00 AM 10/20/17, 9:00 AM 1h 100% Mark
4.2.8) Minutes Compile 10/27/17, 8:00 AM 10/27/17, 9:00 AM 1h 100% Mark
4.2.9) Minutes Compile 11/3/17, 8:00 AM 11/3/17, 9:00 AM 1h 100% Mark
4.2.10) Minutes Compile 11/10/17, 8:00 AM 11/10/17, 9:00 AM 1h 100% Mark
4.2.11) Minutes Compile 11/17/17, 8:00 AM 11/17/17, 9:00 AM 1h 100% Mark
4.2.12) Minutes Compile 11/24/17, 8:00 AM 11/24/17, 9:00 AM 1h 100% Mark
4.3) WEEKLY UPLOADS 9/10/17, 6:00 PM 11/19/17, 7:00 PM 1,033.5h 100%
4.3.1) Moodle upload 9/10/17, 6:00 PM 9/10/17, 7:00 PM 1h 100% Andy
4.3.2) Moodle upload 9/17/17, 6:00 PM 9/17/17, 7:00 PM 1h 100% Andy
4.3.3) Moodle upload 9/24/17, 6:00 PM 9/24/17, 7:00 PM 1h 100% Curtis
4.3.4) Moodle upload 10/1/17, 6:00 PM 10/1/17, 7:00 PM 1h 100% Curtis
4.3.5) Moodle upload 10/8/17, 6:00 PM 10/8/17, 7:00 PM 1h 100% Curtis
4.3.6) Moodle upload 10/15/17, 6:00 PM 10/15/17, 7:00 PM 1h 100% Curtis
4.3.7) Moodle upload 10/22/17, 6:00 PM 10/22/17, 7:00 PM 1h 100% Curtis
4.3.8) Moodle upload 10/29/17, 6:00 PM 10/29/17, 7:00 PM 1h 100% Curtis
4.3.9) Moodle upload 11/5/17, 6:00 PM 11/5/17, 7:00 PM 1h 100% Curtis
4.3.10) Moodle upload 11/12/17, 6:00 PM 11/12/17, 7:00 PM 1h 100% Curtis
4.3.11) Moodle upload 11/19/17, 6:00 PM 11/19/17, 7:00 PM 1h 100% Curtis
5) CLASS RELATED 9/15/17, 8:00 AM 5/4/18, 10:45 PM 3,422h 10.99%
5.1) SOW 9/15/17, 8:00 AM 9/15/17, 9:00 AM 1h 100% Andy; Curtis; Mark
5.2) WBS 9/16/17, 11:00 AM 9/16/17, 12:00 PM 1h 100% 5.1 Andy
5.3) Deliverables 9/22/17, 8:00 AM 9/22/17, 9:00 AM 1h 100% 5.2 Andy
5.4) Budget 9/22/17, 2:00 PM 9/22/17, 3:00 PM 1h 100% 5.3 Mark
5.5) Schedule 9/23/17, 6:00 PM 9/23/17, 9:00 PM 3h 100% 5.4 Curtis
5.6) SSR 9/29/17, 8:00 AM 10/10/17, 4:00 PM 170.25h 100%
5.6.1) SRR Preperation 9/29/17, 8:00 AM 10/6/17, 10:45 PM 118h 100%
5.6.2) Pratice SRR Presentation 10/7/17, 11:00 AM 10/7/17, 11:00 AM 100% 5.6.1 Mark; Andy; Curtis
5.6.3) SRR/CoDR Presentation 10/10/17, 4:00 PM 10/10/17, 4:00 PM 100% 5.6.1
5.7) PDR 11/5/17, 8:00 AM 5/1/18, 10:45 PM 2,625.5h 0% 5.6.3
5.7.1) PDR Preperation 4/1/18, 8:00 AM 5/1/18, 10:45 PM 457.25h 0%
5.7.2) Pratice PDR Pdresentation 11/25/17, 11:00 AM 11/25/17, 11:00 AM 0% 5.7.1 Mark; Andy; Curtis
5.7.3) PDR Presentation 11/28/17, 3:00 PM 11/28/17, 3:00 PM 0% 5.7.1
5.8) FDR 4/10/18, 1:00 PM 5/4/18, 10:45 PM 363.75h 0% 5.7, 5.8.1
5.8.1) FDR Preperation 4/10/18, 8:00 AM 5/4/18, 10:45 PM 368.75h 0%
5.9) Expo 5/4/18, 8:00 AM 5/4/18, 10:45 PM 14.75h 0%
5.10) Fall Final Presentation Upload 4/25/18, 8:00 AM 4/30/18, 9:00 PM 86.75h 0% Mark; Andy; Curtis
5.11) Computer Tool Competency Upload 12/3/17, 2:00 PM 12/3/17, 4:00 PM 2h 100% Mark; Andy; Curtis
5.12) Peer/Self Eval Upload 12/3/17, 2:00 PM 12/3/17, 3:00 PM 1h 100% Mark; Andy; Curtis
5.13) Fall Final Report Upload 12/4/17, 8:00 AM 12/4/17, 8:00 AM 100% Mark; Andy; Curtis
6) IMPORTANT DATES 12/5/17, 8:00 AM 5/18/18, 7:00 PM 2,430h 77.92%
6.1) Fall Final Exams 12/5/17, 8:00 AM 12/9/17, 7:00 PM 70h 100% Mark; Andy; Curtis
6.2) Fall Semester Ends 12/15/17, 8:00 AM 12/15/17, 8:00 AM 0%
6.3) Spring Classes Begin 1/22/18, 8:00 AM 1/22/18, 8:00 AM 100%
6.4) Spring Final Exams 5/14/18, 8:00 AM 5/18/18, 7:00 PM 70h 0% Mark; Andy; Curtis
6.5) Winter Break 12/15/17, 8:00 AM 1/3/18, 10:45 PM 295h 100%
6.6) Winter Session 1/4/18, 8:00 AM 1/19/18, 10:45 PM 236h 100%